Work Progresses on Community Turbine

turbine_site_worksWork is progressing well at the Ruaig site. Stage 1 (Access Road and Crane Pad) has been successfully completed by Agrimarine.

Stage 2 (Foundation Base) is now in progress. In simple terms, this stage consists of digging out a large hole, fabricating a metal frame, and pouring a large amount of concrete. The end result, after two or three weeks to set, is a large circular base on which the turbine will be bolted. It’s obviously a lot more technical than that and the team from Raymond Brown Construction, assisted by I A Mackinnon Haulage/Plant Hire, are working very professionally at the site to complete stage 2 on time.

In the coming few weeks a long articulated vehicle will come to the island to carry out a trial run up from Gott Pier to the Ruaig site. This will help to specifically define areas where road works are required to allow the vehicles carrying the turbine and crane to reach the site. Hopefully, all going to plan, the turbine and crane will arrive on the island around the middle of October. When the turbine and crane arrive on island there will be unavoidable disruption and delay on the roads from the pier to the site. Once dates are confirmed we will be able to give a more detailed time schedule to all.

Hopefully this information provides a general update and we apologise in advance for any inconvenience caused. If you have any concerns or wish more details regarding any stage of the process please get in touch with Liz at the Trust Office 01879 220074 or any of the Tiree Renewable Energy Company Ltd Directors.

Updated: September 16, 2009 — 6:55 pm

Leave a Reply

Struthan Cottages, Isle of Tiree © 2023 Frontier Theme
%d bloggers like this: